Owner’s engineer for hybrid solar thermal and biomass power plant, Spain
Les Borges Blanques Hybrid Solar Thermal and Biomass Power Plant has 336 parabolic trough collectors covering 67 ha with a power rating of 25 MWe, combined with a power plant firing forestry biomass comprising two boilers rated at 2x22 MWth. An auxiliary natural gas boiler is rated at 6 MWth. This allows electricity to be generated day and night as well as during low insolation periods. Fichtner renders owner’s engineering services after contract award to the EPC contractor.
Our services
- Design review
- Workshop inspections of main equipment
- Site supervision
- Supervision of commissioning and trial run
Technical data
- Thermal generation capacity biomass plant: 2 x 22 MWth
- Efficiency: 78%